Digital Goa, July 31 – Goa Tamnar Transmission Project Limited (GTTPL) has issued a public notice inviting objections and suggestions on the proposed alignment of the remaining Goa section of the Goa-Tamnar Power Transmission Project. The notice pertains to the LILO of one circuit of the Narendra (existing)–Narendra (New) 400 kV double-circuit quad transmission line at Xeldem, the only pending component of the project in Goa. The alignment was realigned in accordance with the Supreme Court’s directions of April 7, 2022, and passes through Dharbandora and Mollem before entering Karnataka. GTTPL proposes to seek powers under Section 164 of the Electricity Act, 2003 to execute the transmission line works. Members of the public can inspect the route alignment at the company’s registered office and submit objections or suggestions within two months.