Digital Goa, Apr 2- The Goa government will request additional time from the Court to complete the Taad-Maad stretch of Smart City work at St. Inez, aiming for completion by May-end, informed Advocate General Devidas Pangam. He stated that work on a crucial 12-meter sewerage line has been delayed as a parallel sewerage line and a gas pipeline need protection from damage. “The work there is delicate,” he explained. The government also informed the Court that all other road and sewerage projects are completed as per the chart submitted earlier, except for a few locations facing technical issues.